The construction and operation of the pipeline is a cornerstone in the relationship between the state and the investor.
On the one hand, the pipeline is of particular interest to the state:
- from the point of view of acquiring property;
- from the point of view of controlling the investor's spending and implementing programs;
- from the point of view of a separate investment project;
- from the point of view of expanding the infrastructure, which is a component of energy security.
At a time when, for an investor under a production sharing agreement, a pipeline is a means to achieve hydrocarbon production goals.
Given the circumstances of the construction and operation of the pipeline and the launch of the extraction project, the state interest outweighs the investor interest.
However, there are limits to everything, including the state's interest in commissioning the pipeline.
In my opinion, a good position was highlighted by the Delhi High Court in the case of Nico Resources Limited v. Gujarat State Petrolium Corporation dated August 6, 2020.
The court gave a clear answer to the age-old question of who will be responsible for the constructed and commissioned pipeline.
Neither the government nor the investor should resort to interim measures against each other.
The pipeline is subject to the operating agreement concluded in implementation of the production sharing agreement, and violations of the production sharing agreement will follow from violations of the operating agreement itself.