Based on the approved technological indicators for the field development, project documents are prepared for its development (up to 5 years).
In the project documents for development (first phase), issues of collecting, preparing, and transporting main and by-product products, as well as disposing of formation water, are addressed.
The pilot-industrial development project should include:
- the geological structure of the deposit or exploration area (stratigraphy, tectonics, characteristics of reservoir properties of productive horizons, physicochemical characteristics of oil, gas, and formation water);
- initial geological and industrial information for designing technological parameters (results of hydrodynamic studies, parameters of physical and chemical characteristics of fluids, study of thermobaric conditions);
- field development technology;
- equipment and technology for advancing wells (field development mode, choice of development system);
- key technical and economic indicators of the field.
Economic indicators for development options are calculated based on the level of hydrocarbon production. The results of exploration and prospecting work serve as the initial information for preparing pilot-industrial development projects.
In pilot-industrial development projects, the geological-structural plans of productive wells are justified to complete the geological cycle.
In the technical document for the pilot-industrial development, the following are justified:
- the necessity of drilling advance wells;
- the levels of oil and gas production, condensate, water, and injection of working agents for reservoir impact.
- filtration-capacity properties of productive horizons.