Basics of safe well operation in production sharing agreements

In accordance with the "Rules for the Development of Oil and Gas Fields", approved by Order of the Ministry of Ecology and Natural Resources No. 118, dated March 15, 2017 (hereinafter referred to as the Rules), a systematic set of works and research is provided for, which must be carried out for the safe operation and effective maintenance of wells as a whole.

1) a device for sampling wells; 

2) individual measurement of oil, gas and condensate flow; 

3) individual removal of formation, condensation and technical water (echometry, dynamometry, descent of deep instruments, etc.).

Meanwhile, to the provisions of Article 46 of the Law of Ukraine “On Oil and Gas”, the elimination of emergency releases of gas, oil or formation water from a well is carried out by users of oil and gas-bearing subsoil who drill exploratory and production oil and gas wells, as well as develop oil and gas fields and operate underground gas storage facilities.

The Rules provide for the mandatory conduct of capital and routine well work.

Major repairs include work related to: 

1) changing the well operation facility; 

2) attaching loose selectors; 

3) restoring the casing tightness and eliminating its deformation; 

4) drilling the second well; 

5) intensifying the inflow of hydrocarbons; 

6) limiting the inflow of reservoir and injected water; 

7) fishing and other work with underground equipment; 

8) preserving, de-preservation and liquidation of the well.

In turn, current repairs include work that:

1) is related to the transfer of wells from one mode of operation to another;

2) work to ensure the specified technological mode of operation of underground operational equipment;

3) work to replace equipment;

4) clean the wellbore and tubing from sand;

5) сlean paraffin and salts;

6) perform a scheduled inspection of tubing.

Among other things, during well operation, there is a need to inject a corrosion inhibitor into the annulus of the well, before which water samples are taken to determine the content of iron and manganese ions, water density, pH level, etc.

These procedures are carried out for the safe operation and maintenance of wells. 

Failure to carry out these procedures may result in negative environmental, economic and man-made consequences.