Organization of work at the underground gas storage station

By the time the underground gas storage facility is launched into cyclic operation with design parameters, the arrangement of all main structures ensuring the operation of the artificial gas deposit during gas injection and withdrawal must be completed.

The underground gas storage facility includes: 

- gas pipeline; 

- compressor facilities; 

- units (compressor shops, gas drying plant); 

- gas collection point; 

- gas preparation plants; 

- intra-industrial pipelines; 

- intra-industrial collectors.

When preparing aquifers for the transfer of explored formations and wells, territorially close to the exploration site, hydrological exploration data is checked.

Responsibility for the functionality of the underground gas storage station should be placed on the chief engineer and the chief engineer.

The technological scheme is determined by the volume and duration of gas injection and withdrawal, the periodicity of the cycle and other indicators that can be the basis for fulfilling the tasks formulated before underground gas storage.

During the operation of the gas storage facility, all wells and gas distribution points must: 

- exclude gas outflows outside the design contour; 

- exclude gas overflows into other horizons; 

- prevent the formation of condensate;

- timely completion of repair work on downhole and wellhead equipment, compressor units, gas cleaning and drying units.

The technological scheme of the gas storage project should determine: 

- volumes of industrial gas injection; 

- well operation mode; 

- procedure and scope of research.

Depending on the complexity of the geological structure of the objects and the degree of their exploration, measures must be developed to ensure the safety of industrial gas injection.

Operation of wells in underground gas storage facilities is permitted only through elevator pipes.